Project Workflow

3 Weeks

Request for Proposal (RFP)

Proposal released with RFI
1 Week

Ideation

Initial sketches, renderings & budgeting
2 Weeks

Prototyping

AR, cardboard and handheld samples
1 Week

Engineering

Solidworks modeling, shop drawings & finishes
8 Weeks

Mockups

Full Scale Mockups
4 Weeks

Feedback

Client Review + Markups
2 Weeks

Refinement

Sketches, renderings & shop drawings
1 Week

Final Design + Final Approval

All renderings, finishes & floorplans are approved
1 Week

Order Placement

Signed quote & deposit invoice
2 Weeks

Shop Drawings

Signed shop drawings
10 Weeks

Manufacturing

Part production in Southern California
2 Weeks

Installation

On-site installation in Seattle