Project Workflow
3 Weeks
Request for Proposal (RFP)
Proposal released with RFI
1 Week
Ideation
Initial sketches, renderings & budgeting
2 Weeks
Prototyping
AR, cardboard and handheld samples
1 Week
Engineering
Solidworks modeling, shop drawings & finishes
8 Weeks
Mockups
Full Scale Mockups
4 Weeks
Feedback
Client Review + Markups
2 Weeks
Refinement
Sketches, renderings & shop drawings
1 Week
Final Design + Final Approval
All renderings, finishes & floorplans are approved
1 Week
Order Placement
Signed quote & deposit invoice
2 Weeks
Shop Drawings
Signed shop drawings
10 Weeks
Manufacturing
Part production in Southern California
2 Weeks
Installation
On-site installation in Seattle